Yates is a 482.8 MW gas interconnection project in Coweta, Georgia with a current status of active.

482.8 MWCapacity
ActiveStatus
SOCOMarket
GasTechnology

Project facts

Canonical nameYates
Queue ID728_8
Statusactive
Source status(V) Under construction, more than 50 percent complete
MarketSOCO
TechnologyGas
Capacity482.8 MW
StateGeorgia
CountyCoweta
Point of interconnection—
Requested (queue) date—
Proposed in-service date2027-02-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerGeorgia Power

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-02proposed_online_date2026-12-012027-02-01medium
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-10-02
Data last materially changed2026-10-02
Page data generated2026-10-12

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata