Young County Energy Storage (26INR0302)

Young County Energy Storage is a 104.5 MW other interconnection project in Young, Texas with a current status of operational. It is proposed to connect at TAP 138 KV BUS AND CREAT NEW BUS BETWEEN MURRAY (792) AND GRAHAM SES (1431) COUNTY : YOUNG .

104.5 MWCapacity
OperationalStatus
YoungMarket
OtherTechnology

Project facts

Canonical nameYoung County Energy Storage
Queue ID26INR0302
Statusoperational
Source statusSS Completed, FIS Completed, No IA
MarketYoung
TechnologyOther
Capacity104.5 MW
StateTexas
CountyYoung
Point of interconnectionTAP 138 KV BUS AND CREAT NEW BUS BETWEEN MURRAY (792) AND GRAHAM SES (1431) COUNTY : YOUNG
Requested (queue) date2024-02-27
Proposed in-service date—
Operational date2028-08-01
Withdrawn date—
DeveloperYoung County Energy Storage LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31developerCSE Storage, LLCYoung County Energy Storage LLClow
2026-08-31phaseSS Completed, FIS Started, No IASS Completed, FIS Completed, No IAlow
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-12

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata