Grant County, Arkansas — Interconnection Projects
The interXdata warehouse tracks 11 interconnection projects in Grant, Arkansas, representing 1,320 MW of requested capacity.
11Total projects
0Active
6Operational
5Withdrawn
1,320 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 8 | 1,240 MW |
| Battery | 3 | 80 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Sheridan 500 kV | J2907 | Solar | 400.0 MW | operational | Grant, Arkansas |
| WHITE BLUFF EHV - WRIGHTSVILLE 115.0kV | J2134 | Solar | 200.0 MW | withdrawn | Grant, Arkansas |
| WOODWARD 115 SUB - AECC GRAPEVINE 115.0kV | J2983 | Solar | 140.0 MW | operational | Grant, Arkansas |
| J1577 Sub (337689) | J3481 | Solar | 100.0 MW | operational | Grant, Arkansas |
| AECC GRAPEVINE - CARTHAGE (AR) 115.0kV | J3788 | Solar | 100.0 MW | withdrawn | Grant, Arkansas |
| Redfield Solar | 69394_REDF1 | Solar | 100.0 MW | operational | Grant, Arkansas |
| HARDIN WEST SS - SHERIDAN 115.0kV | J1577 | Solar | 100.0 MW | operational | Grant, Arkansas |
| Woodward 115kV - H.S. EHV 115 kV | J2072 | Solar | 100.0 MW | withdrawn | Grant, Arkansas |
| Woodward-Grapevine 115kV line | J2993 | Battery | 80.0 MW | withdrawn | Grant, Arkansas |
| Hardin West SS to Sheridan 115 kV | J1607 | Battery | 0.0 MW | operational | Grant, Arkansas |
| MABELVALE EHV to WHITE BLUFF EHV 115kV | J2244 | Battery | 0.0 MW | withdrawn | Grant, Arkansas |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Grant County.
Start tracking with interXdata