St Johns County, Florida — Interconnection Projects
The interXdata warehouse tracks 4 interconnection projects in St Johns, Florida, representing 952 MW of requested capacity.
4Total projects
0Active
2Operational
2Withdrawn
952 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 1 | 729 MW |
| Solar | 2 | 149 MW |
| Solar+Battery | 1 | 74 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| FL Queue Project 420 — Gas in St Johns, Florida | 420 | Gas | 728.8 MW | withdrawn | St Johns, Florida |
| Trailside Solar Center | 62916_1 | Solar | 74.5 MW | operational | St Johns, Florida |
| Southeast Queue Project 266 — Solar in St. Johns, Florida | 266 | Solar | 74.5 MW | operational | St. Johns, Florida |
| FL Queue Project 329 — Solar+Battery in St Johns, Florida | 329 | Solar+Battery | 74.5 MW | withdrawn | St Johns, Florida |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| FPL | 1 | 74 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); fpl-oasis; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.