Bibb County, Georgia — Interconnection Projects
The interXdata warehouse tracks 10 interconnection projects in Bibb, Georgia, representing 328 MW of requested capacity.
10Total projects
0Active
10Operational
0Withdrawn
328 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 2 | 130 MW |
| Battery | 1 | 128 MW |
| Other | 7 | 70 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Robins Air Force Base Solar | 61648_1 | Solar | 128.0 MW | operational | Bibb, Georgia |
| Robins Air Force Base Solar | 61648_2 | Battery | 128.0 MW | operational | Bibb, Georgia |
| Graphic Packaging Intl Macon Mill | 54464_0005 | Other | 40.0 MW | operational | Bibb, Georgia |
| Graphic Packaging Intl Macon Mill | 54464_0004 | Other | 15.9 MW | operational | Bibb, Georgia |
| Graphic Packaging Intl Macon Mill | 54464_0001 | Other | 12.8 MW | operational | Bibb, Georgia |
| Bibb Williams | 67048_SP324 | Solar | 2.3 MW | operational | Bibb, Georgia |
| YKK USA Chestney | 54566_SLD1 | Other | 0.5 MW | operational | Bibb, Georgia |
| YKK USA Chestney | 54566_BWP1 | Other | 0.5 MW | operational | Bibb, Georgia |
| YKK USA Chestney | 54566_SEV1 | Other | 0.3 MW | operational | Bibb, Georgia |
| YKK USA Chestney | 54566_SEV2 | Other | 0.2 MW | operational | Bibb, Georgia |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.