Seward County, Kansas — Interconnection Projects
The interXdata warehouse tracks 7 interconnection projects in Seward, Kansas, representing 462 MW of requested capacity.
7Total projects
0Active
3Operational
4Withdrawn
462 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 4 | 394 MW |
| Gas | 3 | 68 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Cimarron River 115 kV Substation | GEN-2024-218 | Solar | 199.0 MW | withdrawn | Seward, Kansas |
| Walkemeyer - Cimarron 115kV | GEN-2021-087 | Solar | 100.0 MW | withdrawn | Seward, Kansas |
| North Liberal 115kV substation | GEN-2019-059 | Solar | 75.0 MW | withdrawn | Seward, Kansas |
| Cimarron River | 1230_1 | Gas | 50.0 MW | operational | Seward, Kansas |
| North Liberal 115 kV Substation | GEN-2020-082 | Solar | 20.0 MW | withdrawn | Seward, Kansas |
| Cimarron River | 1230_2 | Gas | 15.0 MW | operational | Seward, Kansas |
| Arkalon Ethanol LLC | 58192_ST961 | Gas | 3.0 MW | operational | Seward, Kansas |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Seward County.
Start tracking with interXdata