Fillmore County, Minnesota — Interconnection Projects

The interXdata warehouse tracks 20 interconnection projects in Fillmore, Minnesota, representing 1,130 MW of requested capacity.

20Total projects
0Active
13Operational
7Withdrawn
1,130 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Wind6940 MW
Solar5177 MW
Other710 MW
Gas23 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
MISO Queue Project G890 — Wind in Fillmore, MinnesotaG890Wind200.0 MWwithdrawnFillmore, Minnesota
MISO Queue Project G991 — Wind in Fillmore, MinnesotaG991Wind200.0 MWwithdrawnFillmore, Minnesota
MISO Queue Project G746 — Wind in Fillmore, MinnesotaG746Wind200.0 MWwithdrawnFillmore, Minnesota
MISO Queue Project J141 — Wind in Fillmore, MinnesotaJ141Wind200.0 MWwithdrawnFillmore, Minnesota
Other_J2863Solar125.0 MWwithdrawnFillmore, Minnesota
MISO Queue Project J140 — Wind in Fillmore, MinnesotaJ140Wind100.0 MWwithdrawnFillmore, Minnesota
Fillmore County Solar Project67168_FILCOSolar45.0 MWoperationalFillmore, Minnesota
MISO Queue Project J136 — Wind in Fillmore, MinnesotaJ136Wind40.0 MWwithdrawnFillmore, Minnesota
Fountain64907_511Solar3.0 MWoperationalFillmore, Minnesota
Hazel64906_512Solar3.0 MWoperationalFillmore, Minnesota
Lanesboro1987_4Other2.3 MWoperationalFillmore, Minnesota
Spring Valley2013_3Other2.0 MWoperationalFillmore, Minnesota
Preston (MN)2004_6Gas2.0 MWoperationalFillmore, Minnesota
Spring Valley2013_5Other2.0 MWoperationalFillmore, Minnesota
Spring Valley2013_4Other2.0 MWoperationalFillmore, Minnesota
Spring Valley2013_2Other1.1 MWoperationalFillmore, Minnesota
Preston (MN)2004_5Gas1.1 MWoperationalFillmore, Minnesota
Rushford Village64932_513Solar1.0 MWoperationalFillmore, Minnesota
Preston (MN)2004_4Other0.6 MWoperationalFillmore, Minnesota
Lanesboro1987_2Other0.3 MWoperationalFillmore, Minnesota

Top developers

Developer attribution is not yet resolved for this set.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get an alert when a new project is proposed in Fillmore County.