Lyon County, Minnesota — Interconnection Projects
The interXdata warehouse tracks 45 interconnection projects in Lyon, Minnesota, representing 3,851 MW of requested capacity.
45Total projects
3Active
25Operational
17Withdrawn
3,851 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 23 | 2,301 MW |
| Gas | 5 | 820 MW |
| Solar | 13 | 452 MW |
| Battery | 2 | 255 MW |
| Other | 2 | 23 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| MISO Queue Project J131 — Gas in Lyon, Minnesota | J131 | Gas | 300.0 MW | withdrawn | Lyon, Minnesota |
| Other_ | J3346 | Wind | 250.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project G842 — Wind in Lyon, Minnesota | G842 | Wind | 250.0 MW | withdrawn | Lyon, Minnesota |
| Lyon County - Brookings County 345.0kV | J3894 | Battery | 250.0 MW | operational | Lyon, Minnesota |
| Other_ | J3326 | Wind | 250.0 MW | operational | Lyon, Minnesota |
| MISO Queue Project G841 — Wind in Lyon, Minnesota | G841 | Wind | 250.0 MW | withdrawn | Lyon, Minnesota |
| Lake Yankton to Lyon County 115kV | J3021 | Solar | 235.0 MW | operational | Lyon, Minnesota |
| Lyon County Generating Station | 69537_2 | Gas | 210.0 MW | active | Lyon, Minnesota |
| Lyon County Generating Station | 69537_1 | Gas | 210.0 MW | active | Lyon, Minnesota |
| MISO Queue Project H081 — Wind in Lyon, Minnesota | H081 | Wind | 201.0 MW | operational | Lyon, Minnesota |
| LYON COUNTY | J3749 | Wind | 200.0 MW | operational | Lyon, Minnesota |
| MISO Queue Project J254 — Wind in Lyon, Minnesota | J254 | Wind | 200.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project H083 — Wind in Lyon, Minnesota | H083 | Wind | 200.0 MW | withdrawn | Lyon, Minnesota |
| Lake Yankton to Buffalo Ridge 115kV | J3020 | Wind | 165.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project G520 — Wind in Lyon, Minnesota | G520 | Wind | 150.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project J198 — Wind in Lyon, Minnesota | J198 | Wind | 99.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project J400 — Solar in Lyon, Minnesota | J400 | Solar | 62.5 MW | operational | Lyon, Minnesota |
| Marshall Solar Energy Project | 59875_PV1 | Solar | 62.3 MW | operational | Lyon, Minnesota |
| MISO Queue Project J391 — Gas in Lyon, Minnesota | J391 | Gas | 50.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project J295 — Gas in Lyon, Minnesota | J295 | Gas | 50.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project J305 — Solar in Lyon, Minnesota | J305 | Solar | 50.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project J330 — Solar in Lyon, Minnesota | J330 | Solar | 24.8 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project G489 — Wind in Lyon, Minnesota | G489 | Wind | 20.0 MW | withdrawn | Lyon, Minnesota |
| MISO Queue Project J454 — Wind in Lyon, Minnesota | J454 | Wind | 18.9 MW | withdrawn | Lyon, Minnesota |
| Marshall (MN) | 1993_6 | Other | 18.0 MW | operational | Lyon, Minnesota |
| West Queue Project GI-0601 — Wind in Lyon, Minnesota | GI-0601 | Wind | 10.0 MW | operational | Lyon, Minnesota |
| Marshall Solar Plus LLC | 67545_MARSL | Solar | 10.0 MW | operational | Lyon, Minnesota |
| West Queue Project GI-0606 — Wind in Lyon, Minnesota | GI-0606 | Wind | 10.0 MW | operational | Lyon, Minnesota |
| MISO Queue Project G177 — Other in Lyon, Minnesota | G177 | Other | 5.0 MW | active | Lyon, Minnesota |
| Marshall Solar Plus LLC | 67545_MARST | Battery | 5.0 MW | operational | Lyon, Minnesota |
| MISO Queue Project J155 — Wind in Lyon, Minnesota | J155 | Wind | 4.9 MW | withdrawn | Lyon, Minnesota |
| Marshall Wind 2 LLC | 56824_1 | Wind | 4.2 MW | operational | Lyon, Minnesota |
| Marshall Wind 4 LLC | 56826_1 | Wind | 4.2 MW | operational | Lyon, Minnesota |
| Marshall Wind 3 LLC | 56825_1 | Wind | 4.2 MW | operational | Lyon, Minnesota |
| West Queue Project GI-0914 — Wind in Lyon, Minnesota | GI-0914 | Wind | 3.6 MW | withdrawn | Lyon, Minnesota |
| Marshall Wind 6 LLC | 56828_1 | Wind | 2.1 MW | operational | Lyon, Minnesota |
| Marshall Wind 5 LLC | 56827_1 | Wind | 2.1 MW | operational | Lyon, Minnesota |
| Marshall Wind 1 LLC | 56840_1 | Wind | 2.1 MW | operational | Lyon, Minnesota |
| Novel Shelly Solar LLC (CSG) | 64154_SHLLY | Solar | 1.0 MW | operational | Lyon, Minnesota |
| USS Kass Solar LLC | 63170_KASS | Solar | 1.0 MW | operational | Lyon, Minnesota |
| Aquarius Community Solar | 61710_AQUA | Solar | 1.0 MW | operational | Lyon, Minnesota |
| Antares Community Solar | 61176_FACS1 | Solar | 1.0 MW | operational | Lyon, Minnesota |
| Antares Community Solar | 61176_FACS3 | Solar | 1.0 MW | operational | Lyon, Minnesota |
| Antares Community Solar | 61176_FACS2 | Solar | 1.0 MW | operational | Lyon, Minnesota |
| Timmerman (CSG) | 65974_TIMM | Solar | 1.0 MW | operational | Lyon, Minnesota |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Lyon County.
Start tracking with interXdata