Perry County, Mississippi — Interconnection Projects
The interXdata warehouse tracks 9 interconnection projects in Perry, Mississippi, representing 1,060 MW of requested capacity.
9Total projects
0Active
5Operational
4Withdrawn
1,060 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 5 | 700 MW |
| Battery | 2 | 310 MW |
| Other | 2 | 50 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Hintonville | J2999 | Solar | 250.0 MW | operational | Perry, Mississippi |
| Hintonville 161kV Substation | J2992 | Battery | 160.0 MW | withdrawn | Perry, Mississippi |
| Purvis Bulk 161 - Hintonville 161 161.0kV | J4083 | Battery | 150.0 MW | operational | Perry, Mississippi |
| Purvis Bulk 161 - Hintonville 161 161.0kV | J3447 | Solar | 125.0 MW | withdrawn | Perry, Mississippi |
| Purvis Bulk 161 - Hintonville 161 161.0kV | J3915 | Solar | 125.0 MW | withdrawn | Perry, Mississippi |
| Hintonville 161/69 kV Substation | J2980 | Solar | 100.0 MW | withdrawn | Perry, Mississippi |
| Waynesboro 161 - Hintonville 161 161.0kV | J3028 | Solar | 100.0 MW | operational | Perry, Mississippi |
| Leaf River Cellulose LLC | 10233_GEN1 | Other | 25.2 MW | operational | Perry, Mississippi |
| Leaf River Cellulose LLC | 10233_GEN2 | Other | 25.2 MW | operational | Perry, Mississippi |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Perry County.