Cass County, Nebraska — Interconnection Projects
The interXdata warehouse tracks 17 interconnection projects in Cass, Nebraska, representing 3,669 MW of requested capacity.
17Total projects
9Active
6Operational
2Withdrawn
3,669 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 11 | 2,886 MW |
| Battery | 3 | 401 MW |
| Solar | 3 | 382 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Substation 3740 345 kV | GEN-2024-213 | Gas | 360.0 MW | operational | Cass, Nebraska |
| Substation 3740 345 kV | GEN-2024-212 | Gas | 303.0 MW | operational | Cass, Nebraska |
| Substation 3740 345 kV | GEN-2024-211 | Gas | 303.0 MW | operational | Cass, Nebraska |
| Substation 3740 345 kV | GEN-2023-079 | Gas | 272.7 MW | active | Cass, Nebraska |
| Cass County | 55972_CT-5 | Gas | 264.0 MW | active | Cass, Nebraska |
| Cass County | 55972_CT-3 | Gas | 264.0 MW | active | Cass, Nebraska |
| Cass County | 55972_CT-4 | Gas | 264.0 MW | active | Cass, Nebraska |
| Substation 3740 345 kV | GEN-2023-078 | Gas | 255.0 MW | active | Cass, Nebraska |
| Substation 3740 345 kV | GEN-2023-077 | Gas | 255.0 MW | active | Cass, Nebraska |
| OPPD District, Cass County Power Plant Substation, 345kV Bus | GEN-2021-040 | Battery | 200.0 MW | active | Cass, Nebraska |
| Cass County 345kV Substation | GEN-2018-033 | Battery | 200.0 MW | active | Cass, Nebraska |
| OPPD 345KV Cass County Substation | GEN-2021-108 | Solar | 182.2 MW | active | Cass, Nebraska |
| Cass County | 55972_CT-2 | Gas | 172.5 MW | operational | Cass, Nebraska |
| Cass County | 55972_CT-1 | Gas | 172.5 MW | operational | Cass, Nebraska |
| Sub 1366 - Sub 1258 161 kV | GEN-2023-197 | Solar | 150.0 MW | withdrawn | Cass, Nebraska |
| Elmswood 69kV substation | GEN-2019-010 | Solar | 50.0 MW | withdrawn | Cass, Nebraska |
| BRIGHT Battery | 67122_1 | Battery | 1.0 MW | operational | Cass, Nebraska |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.