Dakota County, Nebraska — Interconnection Projects
The interXdata warehouse tracks 4 interconnection projects in Dakota, Nebraska, representing 364 MW of requested capacity.
4Total projects
1Active
2Operational
1Withdrawn
364 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 3 | 362 MW |
| Battery | 1 | 2 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Twin Church 230 kV Substation | GEN-2023-199 | Solar | 250.0 MW | active | Dakota, Nebraska |
| Twin Church 230 kV Substation | GEN-2024-162 | Solar | 110.0 MW | withdrawn | Dakota, Nebraska |
| South Sioux City Solar | 60823_PV1 | Solar | 2.3 MW | operational | Dakota, Nebraska |
| South Sioux City Energy Storage | 65098_SSCES | Battery | 1.5 MW | operational | Dakota, Nebraska |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Dakota County.
Start tracking with interXdata