Eureka County, Nevada — Interconnection Projects
The interXdata warehouse tracks 13 interconnection projects in Eureka, Nevada, representing 2,209 MW of requested capacity.
13Total projects
4Active
5Operational
4Withdrawn
2,209 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar+Battery | 7 | 1,590 MW |
| Other | 3 | 319 MW |
| Solar | 3 | 300 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| NV Queue Project Company PP — Solar+Battery in Eureka, Nevada | Company PP | Solar+Battery | 350.0 MW | withdrawn | Eureka, Nevada |
| NV Queue Project Company JU — Solar+Battery in Eureka, Nevada | Company JU | Solar+Battery | 300.0 MW | withdrawn | Eureka, Nevada |
| NV Queue Project Company NS — Solar+Battery in Eureka, Nevada | Company NS | Solar+Battery | 300.0 MW | active | Eureka, Nevada |
| TS Power Plant | 56224_001 | Other | 242.0 MW | operational | Eureka, Nevada |
| NV Queue Project Company LY — Solar+Battery in Eureka, Nevada | Company LY | Solar+Battery | 200.0 MW | withdrawn | Eureka, Nevada |
| NV Queue Project Company LZ — Solar+Battery in Eureka, Nevada | Company LZ | Solar+Battery | 200.0 MW | withdrawn | Eureka, Nevada |
| NV Queue Project Company PO — Solar+Battery in Eureka, Nevada | Company PO | Solar+Battery | 140.0 MW | active | Eureka, Nevada |
| NV Queue Project Company KL — Solar in Eureka, Nevada | Company KL | Solar | 100.0 MW | operational | Eureka, Nevada |
| TS Power Plant | 56224_SOL1 | Solar | 100.0 MW | operational | Eureka, Nevada |
| NV Queue Project Company KK — Solar+Battery in Eureka, Nevada | Company KK | Solar+Battery | 100.0 MW | operational | Eureka, Nevada |
| TS Power Plant | 56224_SOL2 | Solar | 100.0 MW | operational | Eureka, Nevada |
| NV Queue Project 26-00453 — Other in Eureka, Nevada | 26-00453 | Other | 38.5 MW | active | Eureka, Nevada |
| NV Queue Project Company KG — Other in Eureka, Nevada | Company KG | Other | 38.5 MW | active | Eureka, Nevada |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); nvenergy-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.