Union County, New Jersey — Interconnection Projects
The interXdata warehouse tracks 89 interconnection projects in Union, New Jersey, representing 10,118 MW of requested capacity.
89Total projects
6Active
60Operational
22Withdrawn
10,118 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 58 | 9,062 MW |
| Other | 9 | 753 MW |
| Battery | 4 | 270 MW |
| Solar | 18 | 33 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Linden VFT-Tosco 230kV | Y2-013 | Gas | 800.0 MW | withdrawn | Union, New Jersey |
| Linden 230 kV or 138 kV | A04 | Gas | 750.0 MW | operational | Union, New Jersey |
| East Towanda 230kV | A48 | Gas | 750.0 MW | withdrawn | Union, New Jersey |
| Linden 230kV | Q74 | Gas | 600.0 MW | withdrawn | Union, New Jersey |
| Linden 230kV | O63 | Gas | 525.0 MW | withdrawn | Union, New Jersey |
| Linden 138kV | C01 | Gas | 436.0 MW | operational | Union, New Jersey |
| Linden 230kV, 138kV | G32_MTX6 | Other | 365.0 MW | withdrawn | Union, New Jersey |
| Linden 230kV | G22_MTX5 | Other | 330.0 MW | operational | Union, New Jersey |
| Linden Generating Station | 2406_2001 | Gas | 315.0 MW | operational | Union, New Jersey |
| Linden Generating Station | 2406_1001 | Gas | 315.0 MW | operational | Union, New Jersey |
| Linden 230 kV | A17 | Gas | 300.0 MW | withdrawn | Union, New Jersey |
| Linden Cogen Uprate | 0516 | Gas | 234.4 MW | withdrawn | Union, New Jersey |
| Tosco-VFT 230kV | AA2-183 | Gas | 234.0 MW | withdrawn | Union, New Jersey |
| Linden Cogen Plant | 50006_GTG6 | Gas | 212.5 MW | operational | Union, New Jersey |
| Tosco-VFT 230kV | Z1-109 | Gas | 208.0 MW | withdrawn | Union, New Jersey |
| Linden Generating Station | 2406_1201 | Gas | 181.4 MW | operational | Union, New Jersey |
| Linden Generating Station | 2406_1101 | Gas | 181.4 MW | operational | Union, New Jersey |
| Linden Generating Station | 2406_2201 | Gas | 181.4 MW | operational | Union, New Jersey |
| Linden Generating Station | 2406_2101 | Gas | 181.4 MW | operational | Union, New Jersey |
| Linden | A52 | Gas | 180.0 MW | withdrawn | Union, New Jersey |
| Linden | A26 | Gas | 180.0 MW | operational | Union, New Jersey |
| PJM Queue Project AH1-722 — Gas in Union, New Jersey | AH1-722 | Gas | 158.1 MW | active | Union, New Jersey |
| Brunswick Energy Storage | 1262 | Battery | 150.0 MW | withdrawn | Union, New Jersey |
| PJM Queue Project AH1-715 — Gas in Union, New Jersey | AH1-715 | Gas | 149.4 MW | active | Union, New Jersey |
| Linden 230kV | AH1-722 - moved to TC2 | Gas | 130.4 MW | active | Union, New Jersey |
| Linden 138kV & 230kV | AH1-715 - moved to TC2 | Gas | 127.2 MW | active | Union, New Jersey |
| Linden 230 kV or 138 kV | A03 | Gas | 120.0 MW | operational | Union, New Jersey |
| Linden 230kV | Y3-108 | Gas | 110.0 MW | withdrawn | Union, New Jersey |
| Brunswick Energy Storage | 0927 | Battery | 100.0 MW | withdrawn | Union, New Jersey |
| Linden Generating Station | 2406_7 | Gas | 96.1 MW | operational | Union, New Jersey |
| Linden Generating Station | 2406_6 | Gas | 96.1 MW | operational | Union, New Jersey |
| Linden Generating Station | 2406_5 | Gas | 96.1 MW | operational | Union, New Jersey |
| Linden Generating Station | 2406_8 | Gas | 96.1 MW | operational | Union, New Jersey |
| Linden Cogen Plant | 50006_GTG2 | Gas | 95.2 MW | operational | Union, New Jersey |
| Linden Cogen Plant | 50006_STG2 | Gas | 95.2 MW | operational | Union, New Jersey |
| Linden Cogen Plant | 50006_GTG4 | Gas | 95.2 MW | operational | Union, New Jersey |
| Linden Cogen Plant | 50006_GTG1 | Gas | 95.2 MW | operational | Union, New Jersey |
| Linden Cogen Plant | 50006_GTG5 | Gas | 95.2 MW | operational | Union, New Jersey |
| Linden Cogen Plant | 50006_STG1 | Gas | 95.2 MW | operational | Union, New Jersey |
| Linden Cogen Plant | 50006_STG3 | Gas | 95.2 MW | operational | Union, New Jersey |
| Linden Cogen Plant | 50006_GTG3 | Gas | 95.2 MW | operational | Union, New Jersey |
| Linden 230kV | Z2-002 | Gas | 61.0 MW | operational | Union, New Jersey |
| Linden | Y3-051 | Gas | 47.0 MW | operational | Union, New Jersey |
| Union County Resource Recovery | 50960_GEN1 | Other | 45.0 MW | operational | Union, New Jersey |
| Linden 230kV | T77 | Gas | 44.0 MW | operational | Union, New Jersey |
| Linden Cogen Uprate | 0671 | Gas | 32.0 MW | withdrawn | Union, New Jersey |
| Linden 1 - 138kV | Z1-058 | Gas | 23.0 MW | operational | Union, New Jersey |
| Linden 2 - 230kV | Z1-059 | Gas | 23.0 MW | operational | Union, New Jersey |
| Kenilworth Energy Facility | 10805_GEN1 | Gas | 22.0 MW | operational | Union, New Jersey |
| Furnace Brook-Hazen Switch Point 34kV | AA2-114 | Battery | 20.0 MW | withdrawn | Union, New Jersey |
| Tosco 230kV | S61 | Gas | 20.0 MW | operational | Union, New Jersey |
| Aldene 230kV | X4-044 | Gas | 17.9 MW | operational | Union, New Jersey |
| Linden | G19 | Gas | 12.0 MW | operational | Union, New Jersey |
| Linden | G18 | Gas | 12.0 MW | operational | Union, New Jersey |
| Bayway Refinery | 56294_FGX | Other | 11.2 MW | operational | Union, New Jersey |
| Merck Rahway Power Plant | 10224_GEN9 | Gas | 10.8 MW | operational | Union, New Jersey |
| Kenilworth Energy Facility | 10805_GEN2 | Gas | 6.8 MW | operational | Union, New Jersey |
| Linden | Y3-046 | Gas | 6.0 MW | withdrawn | Union, New Jersey |
| Linden 26 kV | AC1-066 | Gas | 5.0 MW | withdrawn | Union, New Jersey |
| Merck Rahway Power Plant | 10224_GEN8 | Gas | 5.0 MW | suspended | Union, New Jersey |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| East Coast Power LLC | 3 | 416 MW |
| Parkway Generation Operating, LLC | 2 | 307 MW |
| JERA Americas Inc. | 1 | 100 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; New York ISO — interconnection queue; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Union County.