Logan County, Ohio — Interconnection Projects
The interXdata warehouse tracks 26 interconnection projects in Logan, Ohio, representing 2,541 MW of requested capacity.
26Total projects
1Active
2Operational
23Withdrawn
2,541 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 14 | 1,604 MW |
| Wind | 6 | 549 MW |
| Battery | 3 | 338 MW |
| Solar+Battery | 1 | 40 MW |
| Gas | 1 | 10 MW |
| Other | 1 | 0 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Marysville-Sorenson 765 kV | AF2-137 | Solar | 500.0 MW | withdrawn | Logan, Ohio |
| Marysville-Sorenson 765 kV | AG1-003 | Solar | 400.0 MW | withdrawn | Logan, Ohio |
| Scioto Ridge Wind Farm | 58780_1 | Wind | 249.8 MW | operational | Logan, Ohio |
| Marysville-Sorenson 765 kV | AG1-004 | Battery | 200.0 MW | withdrawn | Logan, Ohio |
| Marysville-Sorenson 765 kV | AG2-013 | Solar | 200.0 MW | withdrawn | Logan, Ohio |
| Marysville - Sorenson 765 kV | AH2-147 | Solar | 119.0 MW | withdrawn | Logan, Ohio |
| MISO Queue Project G756 — Wind in Logan, Ohio | G756 | Wind | 100.8 MW | withdrawn | Logan, Ohio |
| Marysville - Sorenson 765 kV | AH2-010 | Solar | 100.0 MW | withdrawn | Logan, Ohio |
| E. Liberty-Blue Jacket 69kV | S51 | Wind | 99.0 MW | withdrawn | Logan, Ohio |
| PJM Queue Project AH1-320 — Battery in Logan, Ohio | AH1-320 | Battery | 69.0 MW | withdrawn | Logan, Ohio |
| Blue Jacket - Kirby 138 kV | AH1-320 - moved to TC2 | Battery | 69.0 MW | withdrawn | Logan, Ohio |
| Marysville - Sorenson 765 kV | AH1-198 | Solar | 55.0 MW | withdrawn | Logan, Ohio |
| Blue Jacket-Kirby 138 kV | AF1-270 - moved to TC1 | Solar | 50.0 MW | withdrawn | Logan, Ohio |
| PJM Queue Project AF1-270 — Solar in Logan, Ohio | AF1-270 | Solar | 50.0 MW | withdrawn | Logan, Ohio |
| Bellefontaine 69 kV | AH1-416 | Solar | 50.0 MW | withdrawn | Logan, Ohio |
| Liberty - Blue Jacket 69kV | R50 | Wind | 48.0 MW | withdrawn | Logan, Ohio |
| Liberty 69kV | O21 | Wind | 48.0 MW | withdrawn | Logan, Ohio |
| Bellefontaine PV and BESS Project | AG1-323 | Solar+Battery | 40.0 MW | withdrawn | Logan, Ohio |
| Blue Jacket 138 kV | AG1-323 - moved to TC1 | Solar | 40.0 MW | withdrawn | Logan, Ohio |
| Blue Jacket 138 kV | AH1-219 | Solar | 39.9 MW | withdrawn | Logan, Ohio |
| Bellefontaine 69kV | T154 | Gas | 10.0 MW | withdrawn | Logan, Ohio |
| RP Wind | 58630_RPOH | Wind | 3.4 MW | operational | Logan, Ohio |
| Marysville - Sorenson 765 kV | AI2-081 | Solar | 0.0 MW | withdrawn | Logan, Ohio |
| Blue Jacket - Kirby 138 kV | AI2-146 | Solar | 0.0 MW | withdrawn | Logan, Ohio |
| Blue Jacket - Kirby 138 kV | AH1-328 - moved to TC2 | Solar | 0.0 MW | active | Logan, Ohio |
| Blue Jacket to Blue Jacket Tap 69 kV | AG1-493 | Other | — | withdrawn | Logan, Ohio |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Hodson GreenDefine Blue Jacket LLC | 1 | 40 MW |
| Invenergy | 1 | 69 MW |
| Fountain Point Solar Energy LLC | 1 | 50 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Logan County.