Meigs County, Ohio — Interconnection Projects
The interXdata warehouse tracks 14 interconnection projects in Meigs, Ohio, representing 3,221 MW of requested capacity.
14Total projects
0Active
4Operational
10Withdrawn
3,221 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Other | 4 | 2,282 MW |
| Gas | 1 | 652 MW |
| Solar | 9 | 287 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Mountaineer-Belmont 765kV | N42 | Other | 1,200.0 MW | withdrawn | Meigs, Ohio |
| Sporn - Waterford 345kV | P54 | Other | 1,035.0 MW | withdrawn | Meigs, Ohio |
| Sporn-Waterford 345kV | W3-128 | Gas | 652.0 MW | withdrawn | Meigs, Ohio |
| Sporn 138kV | AC2-048 | Solar | 60.0 MW | withdrawn | Meigs, Ohio |
| Racine - Ravenswood 69kV | AI2-024 | Solar | 60.0 MW | withdrawn | Meigs, Ohio |
| Ravenswood-Hemlock 69kV | AC1-082 | Solar | 48.0 MW | operational | Meigs, Ohio |
| Great Bend Solar Project | 67834_GBSP1 | Solar | 48.0 MW | operational | Meigs, Ohio |
| Racine | 6006_1 | Other | 23.7 MW | operational | Meigs, Ohio |
| Racine | 6006_2 | Other | 23.7 MW | operational | Meigs, Ohio |
| Ravenswood - Hemlock 69 kV | AG2-589 - moved to TC2 | Solar | 20.0 MW | withdrawn | Meigs, Ohio |
| Ravenswood-East Bashan Switch 69kV | AC2-036 | Solar | 20.0 MW | withdrawn | Meigs, Ohio |
| PJM Queue Project AG2-589 — Solar in Meigs, Ohio | AG2-589 | Solar | 20.0 MW | withdrawn | Meigs, Ohio |
| Meigs-Ravenswood 69kV | V4-055 | Solar | 11.0 MW | withdrawn | Meigs, Ohio |
| Ravenswood-Hemlock 69kV | AI2-313 | Solar | 0.0 MW | withdrawn | Meigs, Ohio |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Riverlake Energy, LLC | 1 | 20 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Meigs County.
Start tracking with interXdata