Beaver County, Oklahoma — Interconnection Projects

The interXdata warehouse tracks 9 interconnection projects in Beaver, Oklahoma, representing 1,673 MW of requested capacity.

9Total projects
0Active
5Operational
4Withdrawn
1,673 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Wind91,673 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Badger to Woodward 345kV line (approximately fifty (50) miles west of Woodward District EHV 345kV Substation)GEN-2016-001Wind300.3 MWwithdrawnBeaver, Oklahoma
Balko Wind LLC58900_BAL1Wind299.7 MWoperationalBeaver, Oklahoma
Tap Hitchland - Woodward Dbl Ckt (GEN-2011-014 Tap) 345kVGEN-2014-052Wind200.0 MWwithdrawnBeaver, Oklahoma
Beaver County - Woodward EHV Dbl Ckt (Badger) 345kVGEN-2015-082Wind200.0 MWoperationalBeaver, Oklahoma
Ponderosa Wind Energy Center63590_PONDEWind200.0 MWoperationalBeaver, Oklahoma
Bluestem60256_1Wind198.0 MWoperationalBeaver, Oklahoma
GEN-2006-016GEN-2006-016Wind100.0 MWwithdrawnBeaver, Oklahoma
Ponderosa Wind II66155_GP01Wind100.0 MWoperationalBeaver, Oklahoma
Beaver County 345 kV SubstationGEN-2022-148Wind75.0 MWwithdrawnBeaver, Oklahoma

Top developers

Developer attribution is not yet resolved for this set.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.