Caddo County, Oklahoma — Interconnection Projects

The interXdata warehouse tracks 39 interconnection projects in Caddo, Oklahoma, representing 5,068 MW of requested capacity.

39Total projects
3Active
26Operational
9Withdrawn
5,068 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Wind132,193 MW
Gas131,196 MW
Solar7866 MW
Battery5810 MW
Other12 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Southwestern2964_3Gas315.0 MWoperationalCaddo, Oklahoma
Sunshine North to Anadarko 138 kV LineGEN-2022-126Solar305.1 MWwithdrawnCaddo, Oklahoma
Gracemont-Lawton East Side 345kVGEN-2016-091Wind303.6 MWoperationalCaddo, Oklahoma
Caddo Wind64047_46002Wind303.2 MWoperationalCaddo, Oklahoma
Anadarko 138kV SubstationGEN-2022-132Battery300.0 MWwithdrawnCaddo, Oklahoma
Pecan Creek 345kV SubstationGEN-2018-048Solar300.0 MWactiveCaddo, Oklahoma
Gracemont 345kVGEN-2015-093Wind250.0 MWwithdrawnCaddo, Oklahoma
Southwestern Power Station 138 kV Substation (SWS4)GEN-2023-229Wind230.0 MWactiveCaddo, Oklahoma
Gracemont 345 kV SubstationGEN-2023-165Battery210.0 MWwithdrawnCaddo, Oklahoma
Gracemont 345 kV SubstationGEN-2023-164Battery210.0 MWwithdrawnCaddo, Oklahoma
White Rock East Wind Project64341_WREWind201.5 MWoperationalCaddo, Oklahoma
Gracemont-Lawton East Side 345kVGEN-2016-095Wind200.0 MWoperationalCaddo, Oklahoma
GEN-2007-029GEN-2007-029Wind200.0 MWwithdrawnCaddo, Oklahoma
Gracemont 138 kV SubstationGEN-2023-150Solar150.0 MWwithdrawnCaddo, Oklahoma
Anadarko Plant3006_6Gas105.1 MWoperationalCaddo, Oklahoma
Anadarko Plant3006_5Gas105.1 MWoperationalCaddo, Oklahoma
Anadarko Plant3006_4Gas105.1 MWoperationalCaddo, Oklahoma
Minco Wind III, LLC58203_1Wind100.8 MWoperationalCaddo, Oklahoma
Tap Southwestern-Fletcher Tap 138kVGEN-2016-097Wind100.0 MWoperationalCaddo, Oklahoma
Carnegie South 138kVGEN-2021-064Solar100.0 MWactiveCaddo, Oklahoma
Blue Canyon Windpower VI LLC57616_GEN1Wind99.8 MWoperationalCaddo, Oklahoma
White Rock West Wind Project64340_WRWWind99.5 MWoperationalCaddo, Oklahoma
Blue Canyon Windpower V LLC57108_GEN 1Wind99.0 MWoperationalCaddo, Oklahoma
Southwestern2964_5Gas86.5 MWoperationalCaddo, Oklahoma
Southwestern2964_4Gas86.5 MWoperationalCaddo, Oklahoma
Southwestern2964_1Gas84.0 MWoperationalCaddo, Oklahoma
Southwestern2964_2Gas84.0 MWoperationalCaddo, Oklahoma
Minco-Gracemont 345kV lineGEN-2018-109Battery50.0 MWwithdrawnCaddo, Oklahoma
Anadarko Plant3006_11Gas45.0 MWoperationalCaddo, Oklahoma
Anadarko Plant3006_GEN1Gas45.0 MWoperationalCaddo, Oklahoma
Anadarko Plant3006_9Gas45.0 MWoperationalCaddo, Oklahoma
Anadarko Plant3006_GEN2Gas45.0 MWoperationalCaddo, Oklahoma
Anadarko Plant3006_10Gas45.0 MWoperationalCaddo, Oklahoma
Oney 138kV substationGEN-2018-098Battery40.0 MWwithdrawnCaddo, Oklahoma
Minco 345kVGEN-2014-005Wind5.7 MWoperationalCaddo, Oklahoma
Cyril61614_1Solar5.0 MWoperationalCaddo, Oklahoma
Hinton61615_1Solar3.0 MWoperationalCaddo, Oklahoma
Pine Ridge61617_1Solar3.0 MWoperationalCaddo, Oklahoma
Southwestern2964_IC1Other2.0 MWsuspendedCaddo, Oklahoma

Top developers

Developer attribution is not yet resolved for this set.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get an alert when a new project is proposed in Caddo County.

Start tracking with interXdata