Mcnairy County, Tennessee — Interconnection Projects
The interXdata warehouse tracks 16 interconnection projects in Mcnairy, Tennessee, representing 946 MW of requested capacity.
16Total projects
3Active
4Operational
9Withdrawn
946 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 10 | 433 MW |
| Solar+Battery | 2 | 300 MW |
| Battery | 2 | 181 MW |
| Other | 1 | 16 MW |
| Hydro | 1 | 16 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Southeast Queue Project 531 — Solar+Battery in Mcnairy, Tennessee | 531 | Solar+Battery | 200.0 MW | withdrawn | Mcnairy, Tennessee |
| Southeast Queue Project 444 — Solar+Battery in Mcnairy, Tennessee | 444 | Solar+Battery | 100.0 MW | withdrawn | Mcnairy, Tennessee |
| TN Queue Project 25RSC-007 — Battery in McNairy, Tennessee | 25RSC-007 | Battery | 100.0 MW | active | McNairy, Tennessee |
| Southeast Queue Project 543 — Solar in Mcnairy, Tennessee | 543 | Solar | 84.0 MW | withdrawn | Mcnairy, Tennessee |
| Southeast Queue Project 605 — Battery in Mcnairy, Tennessee | 605 | Battery | 81.0 MW | withdrawn | Mcnairy, Tennessee |
| Southeast Queue Project 603 — Solar in Mcnairy, Tennessee | 603 | Solar | 80.0 MW | withdrawn | Mcnairy, Tennessee |
| Southeast Queue Project 646 — Solar in Mcnairy, Tennessee | 646 | Solar | 66.0 MW | withdrawn | Mcnairy, Tennessee |
| TN Queue Project 25RSC-006 — Solar in McNairy, Tennessee | 25RSC-006 | Solar | 62.0 MW | active | McNairy, Tennessee |
| Southeast Queue Project 610 — Solar in Mcnairy, Tennessee | 610 | Solar | 60.0 MW | withdrawn | Mcnairy, Tennessee |
| SR Adamsville | 68224_ADAMV | Solar | 25.0 MW | active | McNairy, Tennessee |
| Southeast Queue Project 237 — Other in Mcnairy, Tennessee | 237 | Other | 16.0 MW | withdrawn | Mcnairy, Tennessee |
| Selmer I | 60555_SELMI | Solar | 16.0 MW | operational | McNairy, Tennessee |
| Southeast Queue Project 233 — Hydro in Mcnairy, Tennessee | 233 | Hydro | 16.0 MW | withdrawn | Mcnairy, Tennessee |
| Selmer Farm LLC | 59188_PV1 | Solar | 15.8 MW | operational | McNairy, Tennessee |
| Mulberry Farm LLC | 59184_PV1 | Solar | 15.8 MW | operational | McNairy, Tennessee |
| Selmer II | 60556_SELM2 | Solar | 8.0 MW | operational | McNairy, Tennessee |
Top developers
Developer attribution is not yet resolved for this set.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; tva-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Mcnairy County.
Start tracking with interXdata