Menard County, Texas — Interconnection Projects
The interXdata warehouse tracks 5 interconnection projects in Menard, Texas, representing 664 MW of requested capacity.
5Total projects
1Active
3Operational
1Withdrawn
664 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 1 | 300 MW |
| Other | 1 | 204 MW |
| Solar | 3 | 160 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Fort McKavett Wind | 20INR0154 | Wind | 300.0 MW | withdrawn | Menard, Texas |
| Black & Gold Energy Storage | 24INR0386 | Other | 203.8 MW | operational | Menard, Texas |
| Callan Solar | 27INR0241 | Solar | 91.0 MW | operational | Menard, Texas |
| Centennial Solar | 26INR0372 | Solar | 61.4 MW | active | Menard, Texas |
| Lampwick | 61872_GEN1 | Solar | 7.5 MW | operational | Menard, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Nextera | 1 | 300 MW |
| Centennial AD 8 LLC | 1 | 61 MW |
| Menard PV, LLC | 1 | 91 MW |
| Black & Gold Energy Storage, LLC | 1 | 204 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.