Wheeler County, Texas — Interconnection Projects

The interXdata warehouse tracks 3 interconnection projects in Wheeler, Texas, representing 1,600 MW of requested capacity.

3Total projects
0Active
1Operational
2Withdrawn
1,600 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Gas11,300 MW
Solar1150 MW
Solar+Battery1150 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
Moon Hammer30INR0077Gas1,300.0 MWoperationalWheeler, Texas
Tap Stateline Demarc - Wheeler 230 kV LineGEN-2023-101Solar150.0 MWwithdrawnWheeler, Texas
SPP Queue Project GEN-2023-101 — Solar+Battery in Wheeler, TexasGEN-2023-101Solar+Battery150.0 MWwithdrawnWheeler, Texas

Top developers

Developer (canonical)ProjectsCapacity
Moon Hammer LLC11,300 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-01

Provenance: ercot-gis-report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; spp-summary-csv. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.