Wilbarger County County, Texas — Interconnection Projects

The interXdata warehouse tracks 4 interconnection projects in Wilbarger County, Texas, representing 4,500 MW of requested capacity.

4Total projects
0Active
0Operational
4Withdrawn
4,500 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Wind14,000 MW
Other2300 MW
Solar1200 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
GEN-2008-031GEN-2008-031Wind4,000.0 MWwithdrawnWilbarger County, Texas
Oklaunion 345 kV subGEN-2017-065Solar200.2 MWwithdrawnWilbarger County, Texas
GEN-2008-095GEN-2008-095Other200.0 MWwithdrawnWilbarger County, Texas
GEN-2008-094GEN-2008-094Other100.0 MWwithdrawnWilbarger County, Texas

Top developers

Developer attribution is not yet resolved for this set.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.