City Of Chesapeake County, Virginia — Interconnection Projects
The interXdata warehouse tracks 56 interconnection projects in City Of Chesapeake, Virginia, representing 9,043 MW of requested capacity.
56Total projects
6Active
8Operational
42Withdrawn
9,043 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Offshore Wind | 3 | 2,489 MW |
| Wind | 3 | 2,489 MW |
| Gas | 6 | 2,118 MW |
| Battery | 12 | 1,320 MW |
| Solar | 32 | 628 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Chesapeake 230 kV | AE2-007 | Gas | 967.6 MW | withdrawn | City Of Chesapeake, Virginia |
| Chesapeake 230kV | AB2-051 | Gas | 840.0 MW | withdrawn | City Of Chesapeake, Virginia |
| CVOW 2, OSS 2 – T2G07 | AF1-124 | Offshore Wind | 836.0 MW | active | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-124 - moved to TC1 | Wind | 836.0 MW | operational | City Of Chesapeake, Virginia |
| CVOW 1, OSS 1 - T1L11 | AF1-123 | Offshore Wind | 833.0 MW | active | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-123 - moved to TC1 | Wind | 833.0 MW | active | City Of Chesapeake, Virginia |
| CVOW 3, OSS 3 – T3G15 | AF1-125 | Offshore Wind | 820.0 MW | active | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-125 - moved to TC1 | Wind | 820.0 MW | operational | City Of Chesapeake, Virginia |
| Fentress- Landstown 230kV | AH2-133 | Battery | 300.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Chesapeake 230kV | AC1-159 | Gas | 250.1 MW | withdrawn | City Of Chesapeake, Virginia |
| Fentress – Sligo 230 kV | AH1-444 | Battery | 200.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Fentress-Sligo 230 kV | AG1-235 | Solar | 192.0 MW | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AG1-359 — Battery in City Of Chesapeake, Virginia | AG1-359 | Battery | 127.5 MW | withdrawn | City Of Chesapeake, Virginia |
| Fentress 230 kV | AG1-359 - moved to TC1 | Battery | 127.5 MW | withdrawn | City Of Chesapeake, Virginia |
| Grassfield-Great Bridge 115kV | AC2-012 | Solar | 118.0 MW | operational | City Of Chesapeake, Virginia |
| Yadkins Energy Center | AE2-156 | Battery | 100.0 MW | active | City Of Chesapeake, Virginia |
| PJM Queue Project AG1-364 — Battery in City Of Chesapeake, Virginia | AG1-364 | Battery | 100.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Fentress- Landstown 230kV | AH2-330 | Battery | 100.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Deep Creek 115 kV | AG1-364 - moved to TC1 | Battery | 100.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Yadkin 115 kV | AE2-156 - moved to TC1 | Battery | 100.0 MW | active | City Of Chesapeake, Virginia |
| Fentress-Landstown 230 kV | AD1-033 | Solar | 70.0 MW | operational | City Of Chesapeake, Virginia |
| Loudoun 115kV | AH2-241 | Battery | 45.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Grassfield 34.5 kV | AF2-057 | Battery | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Grassfield 13.2kV | AB2-086 | Solar | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Elizabeth River 230kV | S91 | Gas | 20.0 MW | operational | City Of Chesapeake, Virginia |
| Fentress 34.5kV | AH1-420 | Solar | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Hickory 34.5kV | AC1-047 | Solar | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Elizabeth River 230kV | S90 | Gas | 20.0 MW | operational | City Of Chesapeake, Virginia |
| Hickory 34.5kV | AA2-180 | Solar | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Grassfield 34.5kV | AC1-147 | Solar | 20.0 MW | operational | City Of Chesapeake, Virginia |
| Hickory 34.5 kV | AE1-027 | Solar | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Old Chapel-Millville 138kV | AD1-158 | Solar | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Hickory 34.5 kV | AD2-186 | Solar | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Elizabeth River 230kV | S92 | Gas | 20.0 MW | operational | City Of Chesapeake, Virginia |
| Hickory 34.5 kV | AG1-383 | Solar | 20.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Fentress 34.5kV | AC2-196 | Solar | 16.7 MW | withdrawn | City Of Chesapeake, Virginia |
| Fentress 34.5kV | AC1-046 | Solar | 15.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Hickory 34.5 kV | AE1-028 | Solar | 12.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Hickory 34.5 kV | AD2-187 | Solar | 12.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Hickory 34.5 kV | AD1-159 | Solar | 12.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Deep Creek 115 kV | AH1-262 | Battery | 0.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Fentress - Sligo 230kV (CIR Increase) | AI2-158 | Solar | 0.0 MW | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-305 — Solar in City Of Chesapeake, Virginia | AH2-305 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-303 — Solar in City Of Chesapeake, Virginia | AH2-303 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-299 — Solar in City Of Chesapeake, Virginia | AH2-299 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-301 — Solar in City Of Chesapeake, Virginia | AH2-301 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-302 — Solar in City Of Chesapeake, Virginia | AH2-302 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-309 — Solar in City Of Chesapeake, Virginia | AH2-309 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-310 — Solar in City Of Chesapeake, Virginia | AH2-310 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-306 — Solar in City Of Chesapeake, Virginia | AH2-306 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-304 — Solar in City Of Chesapeake, Virginia | AH2-304 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-307 — Solar in City Of Chesapeake, Virginia | AH2-307 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-308 — Solar in City Of Chesapeake, Virginia | AH2-308 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-298 — Solar in City Of Chesapeake, Virginia | AH2-298 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-300 — Solar in City Of Chesapeake, Virginia | AH2-300 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
| PJM Queue Project AH2-297 — Solar in City Of Chesapeake, Virginia | AH2-297 | Solar | — | withdrawn | City Of Chesapeake, Virginia |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Virginia Electric and Power Company | 3 | 2,489 MW |
| Fentress Energy Storage, LLC | 1 | 128 MW |
| Yadkins Energy Center, LLC | 1 | 100 MW |
| Crossroads Energy Storage LLC | 1 | 100 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in City Of Chesapeake County.
Start tracking with interXdata