Winnebago County, Wisconsin — Interconnection Projects

The interXdata warehouse tracks 12 interconnection projects in Winnebago, Wisconsin, representing 3,109 MW of requested capacity.

12Total projects
1Active
8Operational
3Withdrawn
3,109 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Gas82,373 MW
Other1530 MW
Solar3206 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
MISO Queue Project J338 — Gas in Winnebago, WisconsinJ338Gas845.0 MWwithdrawnWinnebago, Wisconsin
MISO Queue Project J337 — Gas in Winnebago, WisconsinJ337Gas551.0 MWwithdrawnWinnebago, Wisconsin
MISO Queue Project G100 — Other in Winnebago, WisconsinG100Other530.0 MWwithdrawnWinnebago, Wisconsin
MISO Queue Project E0038 — Gas in Winnebago, WisconsinE0038Gas454.8 MWactiveWinnebago, Wisconsin
Alliant Energy Neenah55135_CT01Gas185.5 MWoperationalWinnebago, Wisconsin
Alliant Energy Neenah55135_CT02Gas185.5 MWoperationalWinnebago, Wisconsin
NeevinJ3155Gas150.0 MWoperationalWinnebago, Wisconsin
FTZGERLDJ3466Solar100.0 MWoperationalWinnebago, Wisconsin
Fitzgerald 138 kVJ1745Solar100.0 MWoperationalWinnebago, Wisconsin
Perch Solar WI, LLC69503_20257Solar6.0 MWoperationalWinnebago, Wisconsin
Winnebago County Landfill Gas50936_EG3Gas0.9 MWoperationalWinnebago, Wisconsin
Winnebago County Landfill Gas50936_EG2RGas0.6 MWoperationalWinnebago, Wisconsin

Top developers

Developer (canonical)ProjectsCapacity
Wisconsin Power and Light Company (WPL)1455 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get an alert when a new project is proposed in Winnebago County.

Start tracking with interXdata