Loup River Public Power Dist — Interconnection Queue Projects
Loup River Public Power Dist is associated with 6 tracked interconnection projects representing 53 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
6Projects
0Active
6Operational
0Withdrawn
53 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Other | 6 | 53 MW |
Geographic footprint
| State | Projects |
|---|---|
| Nebraska | 6 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Columbus | 2260_2 | Other | 15.2 MW | operational | Platte, Nebraska |
| Columbus | 2260_3 | Other | 15.2 MW | operational | Platte, Nebraska |
| Columbus | 2260_1 | Other | 15.2 MW | operational | Platte, Nebraska |
| Monroe (NE) | 2273_1 | Other | 2.6 MW | operational | Platte, Nebraska |
| Monroe (NE) | 2273_3 | Other | 2.6 MW | operational | Platte, Nebraska |
| Monroe (NE) | 2273_2 | Other | 2.6 MW | operational | Platte, Nebraska |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-28
Page data generated2026-08-28
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through Loup River Public Power Dist.