PEC — Interconnection Queue Projects
PEC is associated with 1 tracked interconnection projects representing 123 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
1Projects
1Active
0Operational
0Withdrawn
123 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Battery | 1 | 123 MW |
Geographic footprint
| State | Projects |
|---|---|
| Oklahoma | 1 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Monte Vista 138 kV Substation | ERAS-2025-022 | Battery | 123.0 MW | active | Ada, Oklahoma |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-10-03 | Monte Vista 138 kV Substation | operational_date | 2028-01-15 | — |
| 2026-10-03 | Monte Vista 138 kV Substation | proposed_online_date | — | 2028-06-01 |
| 2026-10-03 | Monte Vista 138 kV Substation | status | operational | active |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-10-11
Page data generated2026-10-11
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.