161 kV BRANCH 5 (Bus # 515316) (GEN-2024-SR2)
161 kV BRANCH 5 (Bus # 515316) is a 72.5 MW battery interconnection project in Franklin County, Arkansas with a current status of active. It is proposed to connect at 161 kV BRANCH 5 (Bus # 515316).
72.5 MWCapacity
ActiveStatus
ARMarket
BatteryTechnology
Project facts
| Canonical name | 161 kV BRANCH 5 (Bus # 515316) |
|---|---|
| Queue ID | GEN-2024-SR2 |
| Status | active |
| Source status | IA FULLY EXECUTED/ON SCHEDULE |
| Market | AR |
| Technology | Battery |
| Capacity | 72.5 MW |
| State | Arkansas |
| County | Franklin County |
| Point of interconnection | 161 kV BRANCH 5 (Bus # 515316) |
| Requested (queue) date | 2024-02-06 |
| Proposed in-service date | 2027-03-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | OG&E |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | active | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata