7CASEY - 7KANSAS 345.0kV is a 200.3 MW wind interconnection project in Coles, Illinois with a current status of operational. It is proposed to connect at 7CASEY - 7KANSAS 345.0kV.

200.3 MWCapacity
OperationalStatus
Market
WindTechnology

Project facts

Canonical name7CASEY - 7KANSAS 345.0kV
Queue IDJ3391
Statusoperational
Source statusActive
Market
TechnologyWind
Capacity200.3 MW
StateIllinois
CountyColes
Point of interconnection7CASEY - 7KANSAS 345.0kV
Requested (queue) date2024-04-10
Proposed in-service date2027-09-15
Operational date2027-09-15
Withdrawn date
Developer
Utility / transmission ownerAMEREN ILLINOIS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.