ALAMO SPRINGS SOLAR 2 (1157)

ALAMO SPRINGS SOLAR 2 is a 50.0 MW solar+battery interconnection project in Kern, California with a current status of withdrawn. It is proposed to connect at Arco Substation 70kV.

50.0 MWCapacity
WithdrawnStatus
Market
Solar+BatteryTechnology

Project facts

Canonical nameALAMO SPRINGS SOLAR 2
Queue ID1157
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologySolar+Battery
Capacity50.0 MW
StateCalifornia
CountyKern
Point of interconnectionArco Substation 70kV
Requested (queue) date2015-04-30
Proposed in-service date
Operational date
Withdrawn date2021-05-17
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.