Alexandrite Storage (24INR0381)

Alexandrite Storage is a 203.0 MW battery interconnection project in Cameron, Texas with a current status of withdrawn.

203.0 MWCapacity
WithdrawnStatus
CameronMarket
BatteryTechnology

Project facts

Canonical nameAlexandrite Storage
Queue ID24INR0381
Statuswithdrawn
Source status—
MarketCameron
TechnologyBattery
Capacity203.0 MW
StateTexas
CountyCameron
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date—
Withdrawn date2026-09-23
Developer—
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-30developerJohnson Energy Storage, LLC—low
2026-10-30poi_name8359 Santa Rosa (S_SNROSA4A) 138kV—low
2026-10-30phaseSS Completed, FIS Started, No IA—low
2026-10-30operational_date2026-12-10—medium
2026-10-30withdrawn_date—2026-09-23high
2026-10-30statusoperationalwithdrawnhigh
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-10-30
Data last materially changed2026-10-30
Page data generated2026-11-26

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata