Alpha Power Phase 2 (29INR0363)

Alpha Power Phase 2 is a 400.1 MW gas interconnection project in Guadalupe, Texas with a current status of active. It is proposed to connect at 345kV 7042 Zorn Substation.

400.1 MWCapacity
ActiveStatus
GuadalupeMarket
GasTechnology

Project facts

Canonical nameAlpha Power Phase 2
Queue ID29INR0363
Statusactive
Source statusSS Started, FIS Started, No IA
MarketGuadalupe
TechnologyGas
Capacity400.1 MW
StateTexas
CountyGuadalupe
Point of interconnection345kV 7042 Zorn Substation
Requested (queue) date2026-07-10
Proposed in-service date2029-12-31
Operational date—
Withdrawn date—
DeveloperPalomino Alpha, LLC
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31new_project—activehigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata