Guadalupe County, Texas — Interconnection Projects
The interXdata warehouse tracks 41 interconnection projects in Guadalupe, Texas, representing 5,606 MW of requested capacity.
41Total projects
3Active
30Operational
0Withdrawn
5,606 MWRequested capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 17 | 2,706 MW |
| Other | 12 | 1,044 MW |
| Solar | 7 | 990 MW |
| Battery | 5 | 866 MW |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Calpine Guadalupe Peakers | 24INR0145 | Gas | 450.0 MW | operational | Guadalupe, Texas |
| Rio Nogales Power Project | 55137_STG1 | Gas | 439.0 MW | operational | Guadalupe, Texas |
| Enfinity Juniper Storage | 29INR0211 | Other | 261.1 MW | operational | Guadalupe, Texas |
| Libra Storage | 68895_LIBR | Battery | 236.3 MW | operational | Guadalupe, Texas |
| Rio Nogales Power Project | 55137_CTG1 | Gas | 223.5 MW | operational | Guadalupe, Texas |
| Rio Nogales Power Project | 55137_CTG3 | Gas | 223.5 MW | operational | Guadalupe, Texas |
| Rio Nogales Power Project | 55137_CTG2 | Gas | 222.0 MW | operational | Guadalupe, Texas |
| Rockridge Solar | 24INR0287 | Solar | 211.2 MW | operational | Guadalupe, Texas |
| Guadalupe Battery Storage Project | 27INR0093 | Other | 210.5 MW | operational | Guadalupe, Texas |
| LIBRA BESS | 22INR0366 | Other | 206.2 MW | operational | Guadalupe, Texas |
| Cachi BESS | 22INR0388 | Battery | 205.5 MW | operational | Guadalupe, Texas |
| Utica Solar | 23INR0192 | Solar | 204.5 MW | suspended | Guadalupe, Texas |
| Utica BESS | 24INR0241 | Battery | 203.9 MW | suspended | Guadalupe, Texas |
| Nockenut Springs Solar 2 | 24INR0007 | Solar | 203.3 MW | operational | Guadalupe, Texas |
| Nockenut Springs Solar 1 | 23INR0088 | Solar | 203.2 MW | operational | Guadalupe, Texas |
| Guadalupe Generating Station | 55153_STG1 | Gas | 201.9 MW | operational | Guadalupe, Texas |
| Guadalupe Generating Station | 55153_STG2 | Gas | 201.9 MW | operational | Guadalupe, Texas |
| Ruedrich BESS | 28INR0391 | Other | 200.6 MW | operational | Guadalupe, Texas |
| Cachi | 65861_CACHI | Battery | 200.0 MW | operational | Guadalupe, Texas |
| Guadalupe Generating Station | 55153_CTG2 | Gas | 171.1 MW | operational | Guadalupe, Texas |
| Guadalupe Generating Station | 55153_CTG1 | Gas | 171.1 MW | operational | Guadalupe, Texas |
| Guadalupe Generating Station | 55153_CTG4 | Gas | 171.1 MW | operational | Guadalupe, Texas |
| Guadalupe Generating Station | 55153_CTG3 | Gas | 171.1 MW | operational | Guadalupe, Texas |
| Aster Solar | 24INR0115 | Solar | 160.5 MW | operational | Guadalupe, Texas |
| Roble BESS | 27INR0117 | Other | 154.3 MW | operational | Guadalupe, Texas |
| Sparkl BESS | 20INR0299 | Battery | 20.0 MW | suspended | Guadalupe, Texas |
| RIO NOGALES AGP UPGRADE CT3 | 20INR0272 | Gas | 19.0 MW | operational | Guadalupe, Texas |
| RIO NOGALES AGP UPGRADE CT1 | 19INR0205 | Gas | 19.0 MW | operational | Guadalupe, Texas |
| RIO NOGALES UPGRADE CT2 repower | 21INR0328 | Gas | 13.0 MW | operational | Guadalupe, Texas |
| Niagara Bottling - Seguin | 64389_NIAGS | Solar | 4.9 MW | operational | Guadalupe, Texas |
| CPS Rio Nogales CT201 Rotor Replacement | 25INR0665 | Gas | 3.1 MW | active | Guadalupe, Texas |
| Rio Nogales CT1 Rotor Replacement | 23INR0483 | Gas | 3.1 MW | active | Guadalupe, Texas |
| CPS Rio Nogales CT301 Rotor Replacement | 24INR0602 | Gas | 3.1 MW | active | Guadalupe, Texas |
| TP 4 | 3586_1 | Other | 2.4 MW | suspended | Guadalupe, Texas |
| GVEC | 70224_GVECS | Solar | 2.0 MW | operational | Guadalupe, Texas |
| Dunlap TP 1 | 3582_2 | Other | 1.8 MW | operational | Guadalupe, Texas |
| Dunlap TP 1 | 3582_1 | Other | 1.8 MW | operational | Guadalupe, Texas |
| Abbott TP 3 | 3581_1 | Other | 1.4 MW | suspended | Guadalupe, Texas |
| Abbott TP 3 | 3581_2 | Other | 1.4 MW | suspended | Guadalupe, Texas |
| Nolte | 3585_1 | Other | 1.2 MW | suspended | Guadalupe, Texas |
| Nolte | 3585_2 | Other | 1.2 MW | suspended | Guadalupe, Texas |
Top developers
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| CPS Energy | 5 | 47 MW |
| Pecan Springs Energy, LLC | 2 | 406 MW |
| Ruedrich BESS | 1 | 201 MW |
| BRP Cachi BESS LLC | 1 | 205 MW |
| Aster Solar | 1 | 160 MW |
| Magnolia Solar Development, LLC | 1 | 211 MW |
| Flexen USA LLC | 1 | 154 MW |
| EG Juniper LLC | 1 | 261 MW |
| Guadalupe Peaking Energy Center, LLC | 1 | 450 MW |
| Guadalupe Power Partners LP | 1 | 210 MW |
| Libra Storage LLC | 1 | 206 MW |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); ERCOT — Generation Interconnection Status (GIS) report; Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get an alert when a new project is proposed in Guadalupe County.