Alpha Power Phase 5 (32INR0007)
Alpha Power Phase 5 is a 400.1 MW gas interconnection project in Guadalupe, Texas with a current status of active. It is proposed to connect at 345kV 7042 Zorn Substation.
400.1 MWCapacity
ActiveStatus
GuadalupeMarket
GasTechnology
Project facts
| Canonical name | Alpha Power Phase 5 |
|---|---|
| Queue ID | 32INR0007 |
| Status | active |
| Source status | SS Started, FIS Started, No IA |
| Market | Guadalupe |
| Technology | Gas |
| Capacity | 400.1 MW |
| State | Texas |
| County | Guadalupe |
| Point of interconnection | 345kV 7042 Zorn Substation |
| Requested (queue) date | 2026-07-10 |
| Proposed in-service date | 2032-12-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Palomino Alpha, LLC |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-31 | new_project | — | active | high |
Explore related data
Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata