Apogee Wind II (24INR0078)
Apogee Wind II is a 47.2 MW wind interconnection project in Throckmorton, Texas with a current status of active. It is proposed to connect at 60791 Perigee Substation 345kV.
47.2 MWCapacity
ActiveStatus
ERCOTMarket
WindTechnology
Project facts
| Canonical name | Apogee Wind II |
|---|---|
| Queue ID | 24INR0078 |
| Status | active |
| Source status | active |
| Market | ERCOT |
| Technology | Wind |
| Capacity | 47.2 MW |
| State | Texas |
| County | Throckmorton |
| Point of interconnection | 60791 Perigee Substation 345kV |
| Requested (queue) date | 2021-07-13 |
| Proposed in-service date | 2027-03-31 |
| Operational date | — |
| Withdrawn date | — |
| Developer | King Creek Wind Farm 3, LLC |
| Utility / transmission owner | ERCOT |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.