Arroyo Del Bisonte Solar (21INR0015)

Arroyo Del Bisonte Solar is a 300.0 MW solar interconnection project in Wharton, Texas with a current status of suspended. It is proposed to connect at tap 345kV 44005 WAP - 44040 Bailey.

300.0 MWCapacity
SuspendedStatus
ERCOTMarket
SolarTechnology

Project facts

Canonical nameArroyo Del Bisonte Solar
Queue ID21INR0015
Statussuspended
Source statussuspended
MarketERCOT
TechnologySolar
Capacity300.0 MW
StateTexas
CountyWharton
Point of interconnectiontap 345kV 44005 WAP - 44040 Bailey
Requested (queue) date2018-05-08
Proposed in-service date2021-04-01
Operational date
Withdrawn date
DeveloperSunchase Power
Utility / transmission ownerERCOT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.