Arthur Kill Upgrade (C24-315)

Arthur Kill Upgrade is a 369.9 MW gas interconnection project in Richmond, New York with a current status of withdrawn. It is proposed to connect at Fresh Kills Substation between breakers BT1-4 and BT1-3.

369.9 MWCapacity
WithdrawnStatus
NYISOMarket
GasTechnology

Project facts

Canonical nameArthur Kill Upgrade
Queue IDC24-315
Statuswithdrawn
Source statuswithdrawn
MarketNYISO
TechnologyGas
Capacity369.9 MW
StateNew York
CountyRichmond
Point of interconnectionFresh Kills Substation between breakers BT1-4 and BT1-3
Requested (queue) date2024-10-03
Proposed in-service date
Operational date
Withdrawn date
DeveloperArthur Kill Power, LLC
Utility / transmission ownerNYISO

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.