ATWELL WEST BESS ADDITION (1146)

ATWELL WEST BESS ADDITION is a 20.0 MW solar+battery interconnection project in Tulare, California with a current status of withdrawn. It is proposed to connect at Olive switching station - Smynra 115 Kv Line.

20.0 MWCapacity
WithdrawnStatus
Market
Solar+BatteryTechnology

Project facts

Canonical nameATWELL WEST BESS ADDITION
Queue ID1146
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologySolar+Battery
Capacity20.0 MW
StateCalifornia
CountyTulare
Point of interconnectionOlive switching station - Smynra 115 Kv Line
Requested (queue) date2015-04-30
Proposed in-service date
Operational date
Withdrawn date2017-05-16
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata