Augustus Solar (0935)

Augustus Solar is a 20.0 MW solar interconnection project in Oneida, New York with a current status of withdrawn. It is proposed to connect at Brothertown - Oriskany Falls 46kV.

20.0 MWCapacity
WithdrawnStatus
EMarket
SolarTechnology

Project facts

Canonical nameAugustus Solar
Queue ID0935
Statuswithdrawn
Source status0
MarketE
TechnologySolar
Capacity20.0 MW
StateNew York
CountyOneida
Point of interconnectionBrothertown - Oriskany Falls 46kV
Requested (queue) date2019-11-01
Proposed in-service date2024-11-30
Operational date
Withdrawn date
DeveloperSED NY Holdings LLC
Utility / transmission ownerNYSEG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.