Bell Song Solar 3 (31INR0009)

Bell Song Solar 3 is a 167.6 MW solar interconnection project in Jim Hogg, Texas with a current status of operational. It is proposed to connect at Tap 345 kV #80079 CRUCE7A - #80355 DELSOL7A ckt 1.

167.6 MWCapacity
OperationalStatus
Jim HoggMarket
SolarTechnology

Project facts

Canonical nameBell Song Solar 3
Queue ID31INR0009
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketJim Hogg
TechnologySolar
Capacity167.6 MW
StateTexas
CountyJim Hogg
Point of interconnectionTap 345 kV #80079 CRUCE7A - #80355 DELSOL7A ckt 1
Requested (queue) date2025-06-19
Proposed in-service date
Operational date2030-08-31
Withdrawn date
DeveloperBell Song Solar, LLC 2
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.