Big Rooter West Storage (26INR0432)

Big Rooter West Storage is a 201.1 MW other interconnection project in Robertson, Texas with a current status of operational. It is proposed to connect at 39950# TNTNP_ONE_3 345 KV .

201.1 MWCapacity
OperationalStatus
RobertsonMarket
OtherTechnology

Project facts

Canonical nameBig Rooter West Storage
Queue ID26INR0432
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketRobertson
TechnologyOther
Capacity201.1 MW
StateTexas
CountyRobertson
Point of interconnection39950# TNTNP_ONE_3 345 KV
Requested (queue) date2024-03-22
Proposed in-service date
Operational date2028-12-01
Withdrawn date
DeveloperBig Rooter West, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata