Biggs BESS (28INR0110)

Biggs BESS is a 200.0 MW other interconnection project in McCulloch, Texas with a current status of operational. It is proposed to connect at 76006 Bow Wood 345 kV.

200.0 MWCapacity
OperationalStatus
McCullochMarket
OtherTechnology

Project facts

Canonical nameBiggs BESS
Queue ID28INR0110
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketMcCulloch
TechnologyOther
Capacity200.0 MW
StateTexas
CountyMcCulloch
Point of interconnection76006 Bow Wood 345 kV
Requested (queue) date2024-07-22
Proposed in-service date
Operational date2028-11-15
Withdrawn date
DeveloperBiggs Battery Facility, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.