Bluefox Solar 2 (28INR0063)

Bluefox Solar 2 is a 401.8 MW solar interconnection project in Matagorda, Texas with a current status of operational. It is proposed to connect at #8754 Zoisite 345kV.

401.8 MWCapacity
OperationalStatus
MatagordaMarket
SolarTechnology

Project facts

Canonical nameBluefox Solar 2
Queue ID28INR0063
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketMatagorda
TechnologySolar
Capacity401.8 MW
StateTexas
CountyMatagorda
Point of interconnection#8754 Zoisite 345kV
Requested (queue) date2024-03-22
Proposed in-service date
Operational date2030-01-17
Withdrawn date
DeveloperIndustrial November Project LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.