Bobcat 115kV (GEN-2016-093)

Bobcat 115kV is a 70.0 MW solar interconnection project in Scotts Bluff, Nebraska with a current status of withdrawn. It is proposed to connect at Bobcat 115kV.

70.0 MWCapacity
WithdrawnStatus
NEMarket
SolarTechnology

Project facts

Canonical nameBobcat 115kV
Queue IDGEN-2016-093
Statuswithdrawn
Source statusWITHDRAWN
MarketNE
TechnologySolar
Capacity70.0 MW
StateNebraska
CountyScotts Bluff
Point of interconnectionBobcat 115kV
Requested (queue) date2016-10-10
Proposed in-service date
Operational date
Withdrawn date2020-09-10
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata