NPPD — Interconnection Queue Projects
NPPD is associated with 248 tracked interconnection projects representing 40,269 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
248Projects
28Active
44Operational
176Withdrawn
40,269 MWRequested capacity
0Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 158 | 23,450 MW |
| Solar | 42 | 8,640 MW |
| Other | 23 | 4,409 MW |
| Gas | 12 | 2,434 MW |
| Battery | 13 | 1,337 MW |
Geographic footprint
| State | Projects |
|---|---|
| Nebraska | 246 |
| South Dakota | 1 |
| Oklahoma | 1 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| 345kV bus of Turtle Creek Substation | GEN-2021-007 | Wind | 600.0 MW | withdrawn | Knox And Cedar, Nebraska |
| GEN-2007-011N02 | GEN-2007-011N02 | Other | 600.0 MW | withdrawn | Lancaster County, Nebraska |
| Gentleman – Red Willow 345kV Line Break | GEN-2018-045 | Solar | 550.0 MW | withdrawn | Banner, Nebraska |
| Olive Creek 345 kV Substation | GEN-2024-021 | Gas | 540.0 MW | operational | Lancaster, Nebraska |
| Keystone 345 kV Substation | GEN-2023-116 | Wind | 500.0 MW | withdrawn | Keith, Deuel, Garden, Nebraska |
| Gerald Gentleman-Red Willow 345kV transmssion line | GEN-2019-007 | Solar | 500.0 MW | withdrawn | Lincoln, Nebraska |
| Olive Creek 345 kV Substation | GEN-2023-224 | Other | 478.0 MW | active | Lancaster, Nebraska |
| New Beatrice Power Station 345 kV | GEN-2023-222 | Other | 478.0 MW | active | Gage, Nebraska |
| Hoskins 345kV | GEN-2016-159 | Wind | 427.8 MW | withdrawn | Stanton, Nebraska |
| Sidney Keystone 345 kV line | GEN-2019-029 | Wind | 404.0 MW | withdrawn | Keith And Deuel, Nebraska |
| GEN-2001-040N | GEN-2001-040N | Other | 400.0 MW | withdrawn | 8 Sites, Nebraska |
| GEN-2008-121N01 | GEN-2008-121N01 | Wind | 400.0 MW | withdrawn | Saline County, Nebraska |
| GEN-2001-039N | GEN-2001-039N | Other | 400.0 MW | withdrawn | Grand Island, Nebraska |
| Gerald Gentleman 345kV switchyard | GEN-2018-066 | Solar | 400.0 MW | withdrawn | Lincoln, Nebraska |
| GEN-2007-011N01 | GEN-2007-011N01 | Other | 400.0 MW | withdrawn | Lancaster County, Nebraska |
| Gerald Gentlemen 345kV Substation | GEN-2019-028 | Solar | 400.0 MW | withdrawn | Lincoln County, Ne, Nebraska |
| Gerald Gentleman-Red Willow 345kV line break | GEN-2018-046 | Wind | 400.0 MW | withdrawn | Banner, Nebraska |
| Gerald Gentleman Station 345kV | GEN-2016-106 | Wind | 400.0 MW | withdrawn | Keith, Nebraska |
| Olive Creek 345 kV Substation | GEN-2024-020 | Gas | 390.0 MW | operational | Lancaster, Nebraska |
| New Beatrice Power Station 345 kV | GEN-2024-022 | Gas | 390.0 MW | operational | Gage, Nebraska |
| GEN-2007-030N | GEN-2007-030N | Gas | 350.0 MW | withdrawn | Sheldon, Nebraska |
| Hoskins-Twin Church 230 kV Line | GEN-2016-116 | Wind | 320.0 MW | withdrawn | Dixon, Nebraska |
| Axtell 345 kV Substation | GEN-2020-011 | Solar | 320.0 MW | active | Funk, Nebraska |
| Hoskins - Twin Church 230kV | GEN-2015-042 | Wind | 320.0 MW | withdrawn | Dixon County, Nebraska |
| McCool 345kV Substation | GEN-2017-210 | Solar | 310.0 MW | withdrawn | Cedar, Nebraska |
| Pauline 345 kV Substation | GEN-2022-175 | Solar | 305.0 MW | withdrawn | Clay And Adams, Nebraska |
| Pauline 345kV Substation | GEN-2017-008 | Solar | 305.0 MW | withdrawn | Nuckolls County, Nebraska |
| Antelope - Hoskins 345 kV Substation | GEN-2018-068 | Wind | 302.4 MW | withdrawn | Madison, Nebraska |
| Ogallala-Sydney 230kV | GEN-2018-017 | Wind | 302.4 MW | withdrawn | Brule, Nebraska |
| Grand Prairie-Grand Island (Holt County NE) 345kV | GEN-2015-023 | Wind | 300.7 MW | operational | Antelope & Wheeler County, Nebraska |
| Gerald Gentleman-Red Willow 345kV line break | GEN-2022-198 | Solar | 300.0 MW | withdrawn | Lincoln, Nebraska |
| Keystone 345 kV Substation | GEN-2023-117 | Wind | 300.0 MW | withdrawn | Keith, Deuel, Garden, Nebraska |
| Holt 345 kV Substation | GEN-2022-200 | Wind | 300.0 MW | withdrawn | Holt, Nebraska |
| Nebraska Public Power District's (NPPD) 345 kV Red Willow substation | GEN-2021-044 | Wind | 300.0 MW | withdrawn | Dundy, Nebraska |
| Tobias 345kV Substation | GEN-2015-088 | Wind | 300.0 MW | operational | Saline, Nebraska |
| Tobias 345kV Substation | GEN-2017-181 | Wind | 300.0 MW | active | Lancaster, Nebraska |
| Shell Creek-Hoskins 345kv Line | GEN-2021-058 | Wind | 300.0 MW | withdrawn | Madison, Nebraska |
| Antelope 345kV substation | GEN-2021-057 | Wind | 300.0 MW | withdrawn | Antelope, Nebraska |
| Gerald Gentleman-Red Willow 345kV line | GEN-2021-060 | Wind | 300.0 MW | withdrawn | Lincoln, Nebraska |
| North Hastings - Grand Island 230 kV line | GEN-2024-349 | Solar | 300.0 MW | withdrawn | Hall, Nebraska |
| Hoskins 345kV | GEN-2016-021 | Wind | 298.5 MW | operational | Dixon County, Nebraska |
| Crooked Creek 230 kV | GEN-2022-050 | Wind | 272.0 MW | withdrawn | Dawson And Buffalo, Nebraska |
| New Beatrice Power Station 345 kV | GEN-2024-023 | Gas | 270.0 MW | operational | Gage, Nebraska |
| Enders 115 kV Substation | GEN-2022-077 | Solar | 255.0 MW | withdrawn | Chase, Nebraska |
| Axtell – Post Rock 345 kV | GEN-2016-050 | Wind | 250.7 MW | operational | Webster Co, Nebraska |
| Twin Church 230 kV Substation | GEN-2023-199 | Solar | 250.0 MW | active | Dakota, Nebraska |
| Shell Creek-Hoskins 345kv Line Break | GEN-2018-083 | Wind | 250.0 MW | withdrawn | Madison, Nebraska |
| Hoskins 345kV Substation | GEN-2017-201 | Wind | 250.0 MW | active | Wayne County, Nebraska |
| GEN-2001-029N | GEN-2001-029N | Gas | 250.0 MW | operational | Beatrice, Nebraska |
| Bobcat 345 kV | GEN-2021-099 | Wind | 250.0 MW | withdrawn | Ellis, Oklahoma |
| Cherry County 345kV | GEN-2013-024 | Wind | 250.0 MW | withdrawn | Cherry, Nebraska |
| GEN-2001-029N1 | GEN-2001-029N1 | Other | 250.0 MW | withdrawn | Hastings, Nebraska |
| Antelope - Hoskins 345 kV line | GEN-2024-140 | Solar | 250.0 MW | withdrawn | Mercer, Nebraska |
| Gerald Gentleman Substation 345 kV | GEN-2020-051 | Solar | 250.0 MW | withdrawn | Sutherland, Nebraska |
| Sweetwater 345kV | GEN-2017-001 | Wind | 250.0 MW | withdrawn | Custer, Nebraska |
| GEN-2006-038N009 | GEN-2006-038N009 | Wind | 250.0 MW | withdrawn | Knox County, Nebraska |
| Sweetwater 345 kV Substation | GEN-2023-133 | Wind | 250.0 MW | withdrawn | Custer, Nebraska |
| NPPD Sidney to Keystone 345 kV Line | GEN-2021-037 | Wind | 244.2 MW | withdrawn | Perkins & Keith, Nebraska |
| Tap on the Sweetwater to Gerald Gentleman 345 kV Line | GEN-2021-073 | Solar | 240.0 MW | withdrawn | Lincoln, Nebraska |
| New GGS Satellite 345 kV Substation | GEN-2022-210 | Solar | 240.0 MW | withdrawn | Lincoln, Nebraska |
| New Beatrice Power Station 345 kV | GEN-2023-223 | Other | 239.0 MW | active | Gage, Nebraska |
| New switching station on Gentleman to Sweetwater 345kV line | GEN-2018-125 | Wind | 231.0 MW | active | Lincoln, Nebraska |
| Hoskins 345kV | GEN-2016-043 | Wind | 230.0 MW | operational | Wayne County, Nebraska |
| Ogallala 230kV | GEN-2013-021 | Wind | 229.5 MW | withdrawn | Keith, Nebraska |
| Moore (GEN-2015-088 Tap)-Pauline 345kV | GEN-2016-096 | Wind | 227.7 MW | withdrawn | Fillmore, Nebraska |
| New GGS Satellite 345 kV Substation | GEN-2022-212 | Solar | 225.0 MW | withdrawn | Lincoln, Nebraska |
| Antelope - Hoskins 345 kV | GEN-2018-131 | Solar | 221.4 MW | active | Pierce, Nebraska |
| GEN-2004-018N | GEN-2004-018N | Other | 220.0 MW | withdrawn | Hastings, Nebraska |
| Olive Creek 345 kV Substation | GEN-2023-225 | Other | 217.0 MW | active | Lancaster, Nebraska |
| Orleans-Holdrege Substation 115kV | GEN-2020-013 | Solar | 215.0 MW | active | Orleans, Nebraska |
| Antelope 115kV | GEN-2013-032 | Wind | 202.5 MW | operational | Antelope, Nebraska |
| Antelope - Hoskins 345 kV | GEN-2018-132 | Solar | 201.6 MW | active | Pierce, Nebraska |
| Meadow Grove 230kV | GEN-2008-086N02 | Wind | 201.0 MW | operational | Antelope County, Nebraska |
| GEN-2008-030N | GEN-2008-030N | Wind | 201.0 MW | withdrawn | Dixon County, Nebraska |
| Hoskins 345 kV Substation via Turtle Creek 345 kV Substation | GEN-2023-216 | Wind | 200.0 MW | withdrawn | Knox And Cedar, Nebraska |
| Geneva 115 kV Substation | GEN-2024-168 | Solar | 200.0 MW | withdrawn | Fillmore, Nebraska |
| Line side tap using three breaker ring bus on 230kV Feeder from Gerald Gentleman to North Platte | GEN-2021-105 | Solar | 200.0 MW | withdrawn | Lincoln, Nebraska |
| Tap Hoskins - Twin Church 230kV | GEN-2012-018 | Wind | 200.0 MW | withdrawn | Dixon County, Nebraska |
| GEN-2007-011N | GEN-2007-011N | Other | 200.0 MW | withdrawn | Lancaster County, Nebraska |
| Wakefield 230kV | GEN-2010-051 | Wind | 200.0 MW | operational | Dixon County, Nebraska |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-12 | Twin Church 230 kV Substation | proposed_online_date | — | 2030-01-15 |
| 2026-08-12 | Twin Church 230 kV Substation | operational_date | 2029-10-16 | — |
| 2026-08-12 | Antelope - Hoskins 345 kV line | status | operational | withdrawn |
| 2026-08-12 | Antelope - Hoskins 345 kV line | withdrawn_date | — | 2026-08-10 |
| 2026-08-12 | Antelope - Hoskins 345 kV line | proposed_online_date | — | 2033-12-30 |
| 2026-08-12 | Antelope - Hoskins 345 kV line | operational_date | 2033-10-03 | — |
| 2026-08-12 | Twin Church 230 kV Substation | status | operational | withdrawn |
| 2026-08-12 | Geneva 115 kV Substation | operational_date | 2033-10-03 | — |
| 2026-08-12 | Geneva 115 kV Substation | proposed_online_date | — | 2033-12-30 |
| 2026-08-12 | Geneva 115 kV Substation | withdrawn_date | — | 2026-08-10 |
| 2026-08-12 | Geneva 115 kV Substation | status | operational | withdrawn |
| 2026-08-12 | Pawnee Lake 115 kV Substation | operational_date | 2028-02-17 | — |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through NPPD.