Brockton Combined Cycle is a 332.0 MW gas interconnection project in Plymouth, Massachusetts with a current status of withdrawn. It is proposed to connect at 115 kV F19 and E20 lines.

332.0 MWCapacity
WithdrawnStatus
SEMAMarket
GasTechnology

Project facts

Canonical nameBrockton Combined Cycle
Queue ID178
Statuswithdrawn
Source statusW
MarketSEMA
TechnologyGas
Capacity332.0 MW
StateMassachusetts
CountyPlymouth
Point of interconnection115 kV F19 and E20 lines
Requested (queue) date2006-11-02
Proposed in-service date2019-05-31
Operational date
Withdrawn date2017-05-25
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata