Broken Bow 115kV (GEN-2006-038N005)
Broken Bow 115kV is a 80.0 MW wind interconnection project in Custer County, Nebraska with a current status of operational. It is proposed to connect at Broken Bow 115kV.
80.0 MWCapacity
OperationalStatus
NEMarket
WindTechnology
Project facts
| Canonical name | Broken Bow 115kV |
|---|---|
| Queue ID | GEN-2006-038N005 |
| Status | operational |
| Source status | IA FULLY EXECUTED/COMMERCIAL OPERATION |
| Market | NE |
| Technology | Wind |
| Capacity | 80.0 MW |
| State | Nebraska |
| County | Custer County |
| Point of interconnection | Broken Bow 115kV |
| Requested (queue) date | 2006-10-17 |
| Proposed in-service date | — |
| Operational date | 2010-12-01 |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | NPPD |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata