Broken Bow 115kV (GEN-2012-039)

Broken Bow 115kV is a 74.9 MW wind interconnection project in Custer, Nebraska with a current status of withdrawn. It is proposed to connect at Broken Bow 115kV.

74.9 MWCapacity
WithdrawnStatus
NEMarket
WindTechnology

Project facts

Canonical nameBroken Bow 115kV
Queue IDGEN-2012-039
Statuswithdrawn
Source statusWITHDRAWN
MarketNE
TechnologyWind
Capacity74.9 MW
StateNebraska
CountyCuster
Point of interconnectionBroken Bow 115kV
Requested (queue) date2012-09-28
Proposed in-service date
Operational date
Withdrawn date2012-12-13
Developer
Utility / transmission ownerNPPD

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.