Brotherton Storage (25INR0432)

Brotherton Storage is a 176.1 MW other interconnection project in Anderson, Texas with a current status of operational. It is proposed to connect at 6937 Tucker Sub 138kV .

176.1 MWCapacity
OperationalStatus
AndersonMarket
OtherTechnology

Project facts

Canonical nameBrotherton Storage
Queue ID25INR0432
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketAnderson
TechnologyOther
Capacity176.1 MW
StateTexas
CountyAnderson
Point of interconnection6937 Tucker Sub 138kV
Requested (queue) date2023-04-19
Proposed in-service date
Operational date2027-05-01
Withdrawn date
DeveloperBT Brotherton Storage, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata