BRP Volans BESS (23INR0071)

BRP Volans BESS is a 206.9 MW other interconnection project in Winkler, Texas with a current status of operational. It is proposed to connect at 11189 Quarry Field SW - 1074 Wink 138kV.

206.9 MWCapacity
OperationalStatus
WinklerMarket
OtherTechnology

Project facts

Canonical nameBRP Volans BESS
Queue ID23INR0071
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketWinkler
TechnologyOther
Capacity206.9 MW
StateTexas
CountyWinkler
Point of interconnection11189 Quarry Field SW - 1074 Wink 138kV
Requested (queue) date2020-08-04
Proposed in-service date
Operational date2027-12-01
Withdrawn date
DeveloperBRP Volans BESS LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata