Buffalo Gap 2 Wind Repower (26INR0625)

Buffalo Gap 2 Wind Repower is a 231.5 MW other interconnection project in Nolan, Texas with a current status of operational. It is proposed to connect at 6216 Bluff Creek 138 kV.

231.5 MWCapacity
OperationalStatus
NolanMarket
OtherTechnology

Project facts

Canonical nameBuffalo Gap 2 Wind Repower
Queue ID26INR0625
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketNolan
TechnologyOther
Capacity231.5 MW
StateTexas
CountyNolan
Point of interconnection6216 Bluff Creek 138 kV
Requested (queue) date2024-12-19
Proposed in-service date
Operational date2027-02-01
Withdrawn date
DeveloperBuffalo Gap Wind Farm 2, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata