Buzzer Butte Solar (29INR0394)
Buzzer Butte Solar is a 242.8 MW solar interconnection project in Kent, Texas with a current status of active. It is proposed to connect at Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911).
242.8 MWCapacity
ActiveStatus
KentMarket
SolarTechnology
Project facts
| Canonical name | Buzzer Butte Solar |
|---|---|
| Queue ID | 29INR0394 |
| Status | active |
| Source status | SS Started, FIS Started, No IA |
| Market | Kent |
| Technology | Solar |
| Capacity | 242.8 MW |
| State | Texas |
| County | Kent |
| Point of interconnection | Tap 345 kV Nova prime (BUS# 59908) to Mhos (BUS# 59911) |
| Requested (queue) date | 2026-09-18 |
| Proposed in-service date | 2030-09-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Origis Development LLC |
| Utility / transmission owner | ERCOT |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-10-30 | new_project | — | active | high |
Explore related data
Source last checked2026-10-30
Data last materially changed2026-10-30
Page data generated2026-11-26
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata